Hoàn thành trước mùa mưa lũ 2026: Thủy điện Đakđrinh nỗ lực sửa chữa tuyến đường tránh ngập

Dakdrinh Hydropower Commits to Completing Flood-Avoidance Road Repair Before 2026 Monsoon Season

Dakdrinh Hydropower Joint Stock Company (PV Power DHC), a subsidiary of PV Power within the Petrovietnam ecosystem, is concentrating resources to accelerate the repair of the road that avoids flooding in Dakdrinh Hydropower Reservoir branch 01. The company is striving to complete and hand over this critical infrastructure to the local community before the 2026 flood season.



Strategic Project for Flood-Prone Region

The flood-avoidance road for Dakdrinh Hydropower Reservoir branch 01 plays a strategic role in connecting transportation networks and ensuring safety for residents in areas affected by the reservoir. The repair of this road not only addresses continuous transportation issues but also contributes to flood prevention, protects agricultural production, and safeguards residents' property.



According to the plan, the project will be implemented over a total length of 5.2km with a total investment of approximately 120 billion VND. The company has established a Project Steering Committee and mobilized top experts to ensure both quality and construction timeline of the project.



Project Background

Dakdrinh Hydropower is located on the Dak Kong River system, spanning Kon Tum and Quang Nam provinces. This hydropower facility plays a crucial role in supplying electricity to the Central Highlands and Central regions while regulating floods and protecting downstream areas.



However, after years of operation, the flood-avoidance road in branch 01 has deteriorated severely, particularly in low-lying sections that frequently flood during the rainy season. This has significantly hindered transportation, production, and daily activities of local residents.



Project Details

The flood-avoidance road repair project for Dakdrinh Hydropower Reservoir branch 01 includes several important components:



  • Upgrading the road surface using cement-treated crushed stone materials
  • Constructing a drainage system along both sides of the road
  • Installing drainage culverts at low-lying points
  • Building embankments to prevent erosion
  • Installing traffic sign systems
  • Equipping the road with energy-saving LED lighting systems

The company is applying modern construction technologies and sustainable materials to ensure the road can withstand the pressure from water flow and heavy rains while minimizing environmental impact.



Special Construction Measures

To ensure completion before the 2026 flood season, the company has implemented special construction measures:



  • Dividing the construction area into small sections for simultaneous implementation
  • Utilizing modern machinery and increasing construction workforce to three shifts
  • Establishing a continuous quality monitoring system
  • Developing contingency plans for adverse weather conditions

Expected Benefits

The completion of this project will bring numerous practical benefits to the local community:



SectorBenefits
TransportationEnsuring 24/7 accessibility, reducing travel time
Disaster PreventionMinimizing flood damage, protecting production and housing
EconomyPromoting local tourism and commercial development
EnvironmentReducing pollution from flooding, protecting ecosystems

Leadership and Community Perspectives

According to Mr. Nguyen Van Hung, Director of Dakdrinh Hydropower Joint Stock Company PV Power DHC: "We fully recognize our responsibility in ensuring the safety of people in downstream areas. The flood-avoidance road repair project is one of our top priorities for the 2025-2026 period."



Ms. Tran Thi Mai, Vice Chairwoman of Dak Glei District People's Committee, Kon Tum Province, shared: "Local residents are eagerly awaiting the completion of this project. The new road will completely transform the lives of our people, especially during the flood season when we were previously isolated."



Implementation Timeline

The company has developed a detailed timeline to ensure the project is completed on schedule:



  • Q1 2025: Complete preparation work, land clearance
  • Q2-3 2025: Implement main construction components
  • Q4 2025: Complete construction, conduct partial inspections
  • Q1 2026: Finalize all components and hand over to local authorities

Conclusion

The flood-avoidance road repair project for Dakdrinh Hydropower Reservoir branch 01 is not merely a regular transportation infrastructure but represents the social responsibility of state-owned enterprise Petrovietnam. With high determination and adequate resources, the company is confident in completing the project on schedule, contributing to improved living standards for local residents and ensuring flood prevention safety for the flood-prone region.



As Vietnam faces increasingly extreme weather conditions, infrastructure projects like this demonstrate the critical role of public-private partnerships in building climate resilience and protecting vulnerable communities.