EVNNPT Thúc Đẩy Tiến Độ Dự Án Đường Dây 220kV Than Uyên - Lào Cai

EVNNPT Accelerates Progress on 220kV Than Uyen - Lao Cai Power Transmission Project

In a significant move to enhance Vietnam's power infrastructure, the National Power Transmission Corporation (EVNNPT) conducted a comprehensive progress review meeting for the 220kV Than Uyen - Lao Cai transmission line project on July 2, 2026. The meeting, chaired by Mr. Hoàng Xuân Khôi, Acting General Director of EVNNPT, brought together all key stakeholders to address implementation challenges and ensure the project stays on track to meet its critical objectives.



Project Overview and Strategic Importance

The 220kV Than Uyen - Lao Cai transmission line represents a vital component in Vietnam's national power grid development strategy. As the nation continues its economic expansion, particularly in northern regions, reliable electricity infrastructure becomes increasingly crucial for sustainable growth. This project specifically aims to enhance power supply stability in Lao Cai province and surrounding areas, which have experienced rapid development in recent years.



EVNNPT, as the state-owned enterprise responsible for operating and developing Vietnam's high-voltage power transmission system, plays a pivotal role in the country's energy sector. The corporation manages over 10,000 kilometers of transmission lines and numerous substations across Vietnam, making it instrumental in the nation's transition toward a more robust and modern power infrastructure.



Meeting Objectives and Key Participants

The July 2, 2026 meeting convened at the project site in Lao Cai province, demonstrating EVNNPT's commitment to on-the-ground problem-solving. The gathering included representatives from EVNNPT's project management board, construction contractors, local authorities, and community leaders. The primary objectives were to:


  • Assess current implementation status against planned timelines
  • Identify and address emerging challenges
  • Coordinate solutions among all stakeholders
  • Reinforce quality control measures
  • Establish clear action plans for immediate issues

Mr. Hoàng Xuân Khôi emphasized the project's national significance during his opening remarks, stating: "This transmission line is not merely infrastructure but a lifeline for economic development in northern Vietnam. We must overcome all obstacles to ensure its timely completion."



Project Goals and Expected Benefits

The 220kV Than Uyen - Lao Cai project was initiated with several key objectives:


  • Enhancing Power Supply Reliability: Strengthening the transmission network to reduce power outages and voltage fluctuations in the region.
  • Supporting Economic Development: Providing stable electricity to support industrial parks, businesses, and new residential developments.
  • Integrating Renewable Energy: Creating infrastructure capacity for future integration of renewable energy sources in the region.
  • Reducing Transmission Losses: Implementing modern technologies to minimize energy loss during transmission.

Upon completion, the project is expected to deliver substantial economic benefits, including improved productivity for local businesses, enhanced quality of life for residents, and attraction of new investment to the region. The enhanced power infrastructure will particularly benefit the tourism sector in Lao Cai province, which has been experiencing significant growth.



Implementation Challenges

Despite its strategic importance, the project has encountered several obstacles that threaten its timely completion. During the meeting, contractors and project managers presented detailed reports on the following challenges:



  • Unseasonal rainfall
  • Mountainous terrain difficulties
  • Complex routing requirements
  • Specialized equipment needs
  • Challenge CategorySpecific IssuesImpact on Project
    Land AcquisitionDelayed consent from some landownersSlowed right-of-way establishment
    Financial ConstraintsInsufficient timely capital allocationMaterial procurement delays
    Weather ConditionsWork stoppages and safety concerns
    Technical IssuesExtended implementation time

    Mr. Khôi acknowledged these challenges but expressed confidence in finding effective solutions: "Every major infrastructure project faces obstacles. What matters is our collective commitment to overcome them while maintaining the highest standards of quality and safety."



    Proposed Solutions and Action Plan

    In response to the identified challenges, EVNNPT and stakeholders developed a comprehensive action plan with the following key initiatives:



    Addressing Land Acquisition Issues

    • Enhanced community engagement through localized information campaigns explaining project benefits
    • Establishing dedicated consultation offices in affected communities
    • Implementing fair and transparent compensation mechanisms
    • Coordination with local authorities to accelerate administrative processes

    Financial Solutions

    • Diversifying funding sources beyond traditional state budgets
    • Exploring public-private partnership opportunities
    • Reallocating internal EVNNPT resources to prioritize this critical project
    • Establishing a contingency fund for unexpected expenses

    Technical and Operational Adaptations

    • Implementing all-weather construction techniques where feasible
    • Increasing workforce and equipment deployment in favorable weather windows
    • Adopting advanced construction methods to minimize weather dependency
    • Implementing rigorous quality control protocols to prevent rework

    Project Timeline and Milestones

    The 220kV Than Uyen - Lao Cai project was originally scheduled for completion in Q4 2026. While recent challenges have created some delays, EVNNPT has established revised milestones to ensure timely delivery:



    MilestoneOriginal TimelineRevised TimelineStatus
    Project ApprovalQ1 2025Q1 2025Completed
    Land Acquisition CompletionQ2 2025Q3 2025In Progress
    Construction StartQ3 2025Q4 2025Pending
    Major Components InstallationQ2-Q3 2026Q3-Q4 2026Pending
    Project CompletionQ4 2026Q1 2027Pending

    Environmental and Social Considerations

    Beyond technical and financial aspects, the project incorporates significant environmental and social considerations. EVNNPT has committed to minimizing the project's ecological footprint through:


    • Implementing erosion control measures along transmission routes
    • Utilizing environmentally friendly construction techniques
    • Establishing wildlife corridors to minimize habitat disruption
    • Providing employment opportunities for local residents
    • Supporting community development initiatives in project-affected areas

    Future Outlook and Regional Impact

    The successful completion of the 220kV Than Uyen - Lao Cai transmission line will mark a significant milestone in Vietnam's power infrastructure development. The enhanced transmission capacity will support the region's economic ambitions while providing a foundation for future renewable energy integration.



    Mr. Khôi concluded the meeting by emphasizing the broader vision: "This project is part of Vietnam's strategic development of its power grid. It will not only serve immediate needs but also lay the groundwork for sustainable growth in northern Vietnam for decades to come."



    As Vietnam continues its economic development journey, infrastructure projects like the 220kV Than Uyen - Lao Cai transmission line demonstrate the nation's commitment to building a modern, reliable, and sustainable energy future. With EVNNPT's leadership and the collaborative efforts of all stakeholders, this project is poised to deliver lasting benefits to the region and contribute to Vietnam's overall economic prosperity.